Short answer
For a continuous footing, multiply total length (ft) × width (ft) × depth (ft) and divide by 27. Example: 120 ft of footing (a 24 × 36 ft perimeter), 16 inches wide and 8 inches deep, needs 3.95 cubic yards.
| 120 ft × 16 in × 8 in | 3.95 cu yd |
|---|---|
| Per 10 ft at 16 × 8 in | 0.33 cu yd |
| Ready-mix | $160–$195+ per cu yd[2] |
Footings with piers or walls
Use the Column / Sonotube tab for round piers and the Wall tab for a stem wall on top of the footing, then add the volumes. Structural footings usually need a permit and inspection. Licensed foundation contractors can confirm the size for your site.
Other concrete calculators
Get free quotes from licensed contractors
Free · No obligation · Licensed contractors only
Step 1 of 3
Frequently asked questions
How do I measure footing length?
+
Add up the length of every side. A 24 × 36 ft rectangle has 2 × 24 + 2 × 36 = 120 ft of footing.
How wide and deep should a footing be?
+
It depends on the load, the soil and local frost depth, so footing size is set by your building code or engineer. Ask your local building department before you dig.
Sources
- [1]QUIKRETE, Concrete Mix No. 1101 data sheet (bag yields) (current data sheet)
- [2]ConcreteNetwork.com, Concrete Prices (updated July 14, 2026)
Prices are national ranges published by the sources above, not quotes. Your price depends on size, access, site preparation and local labor rates. The only way to know is to compare written quotes.